WORK-306
Setting up your dashboard 0 entities found · 7/34 branches scanned
ID:WORK-306Status:done

Plan plugin migration to metaFields + zones

Phase 1 proof case for SPEC-079. Migrates the plan plugin's entity runes (work, bug, spec, decision, milestone) from the legacy slots + structure config shape to the new metaFields + zones + sections model. Lands together with WORK-305 so v0.18 ships the spec end-to-end.

Priority:mediumComplexity:moderateMilestone:v0.17.0Source:SPEC-079

Criteria completion

Criteria completion: 9 of 9 (100%) checked; tracking started on Jun 1, no incremental history yet0%25%50%75%100%Jun 1Jun 15

Tracking started Jun 1 — check back for trends.

Acceptance Criteria

  • plugins/plan/src/config.ts rewritten. Each of the five entity runes (Work, Bug, Spec, Decision, Milestone) replaces its slots: [...entitySlots] + structure: { … } block with:

    • metaFields declaring each field's metaType, metaRank, label, condition, tag (for <time> etc.), and sentimentMap where applicable.
    • zones.eyebrow = { left: ['id'], right: ['status'] } for the primary header.
    • zones.metadata = { fields: [...] } for the descriptive header (priority, complexity, assignee, milestone, source, created, modified, tags — varies per entity type).
    • sections.title, sections.blurb, sections.body retained as today.
  • entitySlots constant deleted. The slots: [...entitySlots] array is no longer needed (engine derives render order from the canonical vocabulary).

  • Per-entity field shapes mirror today's behaviour.

    • Work: id, status, priority, complexity, assignee, milestone, source, created, modified, tags. Eyebrow: id+status. Metadata: the rest.
    • Bug: id, status, severity, assignee, milestone, source, created, modified, tags. Eyebrow: id+status. Metadata: the rest.
    • Spec: id, status, version, supersedes, created, modified, tags. Eyebrow: id+status. Metadata: the rest.
    • Decision: id, status, date, supersedes, source, created, modified, tags. Eyebrow: id+status. Metadata: the rest.
    • Milestone: name (used as id), status, date, target, done / total counts (from WORK-281 rollup), created, modified, tags. Eyebrow: name+status. Metadata: the rest.
    • sentimentMap values preserved verbatim from today's config.
  • plugins/plan/src/index.ts theme.runes entry updated. The exported theme config for the plugin reflects the new shape. Existing per-rune CSS (work.css, bug.css, etc.) inspected for selectors that referenced the old class names (__header-primary, __header-secondary); rewritten to the new zone-named selectors (__eyebrow, __metadata).

  • Rune-specific CSS quirks preserved. Complexity dots on work ([data-complexity="…"] > .rf-work__metadata > .rf-work__complexity dd::after) continue to render correctly under the new DOM. Assignee @ prefix preserved. Body section dividers untouched.

  • Plan-site rendering passes. All existing plan-site snapshot tests in packages/content/test/plan-site-dogfood-real.test.ts pass with the new DOM shape (zone-named classes, def-list metadata). Visual QA on a representative work / bug / decision / spec / milestone page in the rendered plan site.

  • Backwards-compat shim NOT exercised by plan plugin itself. Plan plugin is fully migrated; the shim only catches third-party consumers (which the plan plugin is not). Verify via the shim's first-encounter warning — it should not fire for any plan rune.

  • Plan plugin tests updated. Tests in plugins/plan/test/ that snapshot rune output reflect the new DOM. Scanner tests untouched (they read frontmatter / rune attributes, not output DOM).

  • Docs. Plan-rune doc pages (site/content/runes/plan/{spec,work,bug,decision,milestone}.md) updated:

    • Output contract snippets reflect the new DOM (zone-named classes, def-list metadata).
    • Any examples referencing __header-primary etc. updated to __eyebrow / __metadata.

Approach

Mechanical config rewrite + selective CSS adjustment. The work splits into per-entity passes that can land as small commits:

  1. Work: the canonical case. Migrate first to validate the shape and lock the test approach.
  2. Bug: similar shape, smaller field set.
  3. Spec: simpler — only id+status in eyebrow, fewer metadata fields.
  4. Decision: similar to spec.
  5. Milestone: the outlier (name as id, integrates with WORK-281 progress rollup).

Each pass is small enough to review independently. CSS sweep follows the config migration (rename class selectors). Snapshot tests get regenerated last after all five entities migrate.

Dependencies

  • WORK-305 — engine + layout primitives must land first (or in the same merge train). Without it, the new config shape has no consumer.

References

  • SPEC-079 — the spec being implemented.
  • WORK-281 — milestone progress rollup, the source of checkedCount / totalCount on milestone entities.

Resolution

Completed: 2026-06-01

Branch: claude/spec-079-implementation (same branch as WORK-305 — Phase 1 lands together).

What was done

Plan plugin config (plugins/plan/src/config.ts):

  • Rewrote all five entity runes (Spec, Work, Bug, Decision, Milestone) from legacy slots: [...entitySlots] + structure: { 'header-primary': …, 'header-secondary': … } to SPEC-079 metaFields + zones + contentSlots.
  • Eyebrow zone declared as { left: ['id'], right: ['status'] } for all entities (Milestone uses name as id). Metadata zone declared with the appropriate field list per entity.
  • entitySlots constant removed — engine derives render order from canonical vocabulary (eyebrow → title → blurb → metadata → body).
  • projection: preambleProjection removed — engine auto-derives the .rf-{block}__preamble wrapper around header positions.
  • Per-rune editHints collapsed to { body: 'none' } — per-field hints ('id-badge': 'none' etc.) no longer needed since the engine derives row identity from data-field.
  • sentimentMap values preserved verbatim from the old config.

Per-rune CSS (packages/lumina/styles/runes/):

  • work.css, bug.css, spec.css, decision.css, milestone.css — renamed __header-primary / __header-secondary selectors to __eyebrow / __metadata. Layout geometry comes from [data-zone-layout=…] selectors (universal), so per-rune CSS now carries only spacing and rune-specific quirks.
  • Work-specific quirks preserved: complexity dots now target .rf-work__metadata [data-field="complexity"] dd::after (with content driven by [data-complexity=…] on the work root). Assignee @ prefix targets [data-field="assignee"] dd::before.

Tests + docs:

  • All existing plan-site snapshot tests (packages/content/test/plan-site-dogfood-real.test.ts, plan-site-dogfood.test.ts) pass with the new DOM shape — the snapshots re-derive from the live config so the rename rides along.
  • Plan plugin's own tests (plugins/plan/test/{work,bug,spec,decision,milestone,plan-config}.test.ts) all pass — they read frontmatter / rune attributes, not output DOM.
  • Plan-rune doc pages (site/content/runes/plan/{work,bug,spec,decision,milestone}.md) have no __header-primary / __header-secondary references — nothing to update there.

Notes

  • Plan plugin no longer uses the backwards-compat shim — it's fully migrated to SPEC-079. Verified the warnLegacySlots first-encounter warning doesn't fire for any plan rune (it only triggers when a rune has config.slots + config.structure AND legacy slot names, neither of which the plan plugin sets anymore).
  • Field name mapping was a 1-to-1 carry-over — every modifier the legacy config declared has a matching metaFields entry. The engine reads the value via the existing modifier-from-meta machinery and renders it via the new layout primitives. No data-flow changes; only the rendering shape moved from plugin to theme.
  • Milestone uses name instead of id — the milestone rune's identifier modifier is name (not id), so its metaFields.name = idField and zones.eyebrow.left = ['name']. The rendered DOM is identical to other entities (left slot = monospace identifier, right slot = sentiment-tinted status chip).
  • Per-field condition — fields like assignee, milestone, source, created, modified, tags use condition to render only when the corresponding modifier has a value. Same conditional-rendering semantics as the legacy structure[…].condition field.
  • Contracts regeneratedcontracts/structures.json (main site) and packages/lumina/contracts/structures.json (Lumina theme test surface) both updated to reflect the new DOM shape. The plan rune contracts now show zones + contentSlots instead of slots + structure.